Charger Requirements
At least 2 Emporia EV chargers (cannot create network with just 1)
All chargers must be online during setup
Each charger can only be in one network at a time
Electrical Requirements
Network Max Amps must be less than 400A
Minimum 6A per charger (Network Max Amps ≥ 6A × number of chargers)
Never exceed 80% of your circuit breaker or sub-panel capacity when setting Network Max Amps (Example: 40A for 50A breaker)
Quick Setup Checklist
Before creating your network, verify:
At least 2 chargers online in the app
Know your electrical capacity (breaker or sub-panel rating)
Calculated your minimum Network Max Amps needed
Planned chargers are not already assigned to other Load Sharing networks
Network Max Amps Examples
2 chargers: Minimum 12A required (6A × 2)
3 chargers: Minimum 18A required (6A × 3)
4 chargers: Minimum 24A required (6A × 4)
Setting Up Your Network
Open the Emporia Energy app
Tap Discover within the app
Navigate to Load Sharing (available after app version 4.3.0)
Create a new network and give it a name
Set Network Max Amps following the requirements above
Add chargers (must be online to save network settings)
Confirm chargers share electrical capacity when prompted
Save network (requires a minimum of 2 chargers)
Common Setup Errors
"Charger not available" → Charger is offline or firmware needs updating
"Network Max Amps too low"
→ Increase amperage or reduce number of chargers
"Cannot save network" → Need at least 2 chargers in the network
"Charger already in network" → Remove charger from existing network first
Need Help?
If setup fails:
Double-check all requirements above
Restart the Emporia Energy app
Ensure stable internet connection
Contact Emporia Support if issues persist